Aug 02

Work on Tennyson Continues

Posted on August 2, 2019 at 8:36 AM by Andy Pederson

Ditching and stormwater work continues on the north end of Tennyson.  Crews will transition to the south end of Tennyson in the coming week, starting with ditching on the east side of street.  Please use caution as crews will be over excavating ditches initially and backfilling with gravel and other materials to help manage stormwater in low lying areas.   

Landscape restoration is scheduled to begin the week of August 19 throughout the project area with road repaving starting the week of September 9.  
Jul 17

Work begins on Tennyson

Posted on July 17, 2019 at 10:34 AM by Andy Pederson

The 2019 road and stormwater management project is well underway.  All ditch and stormwater work has been completed on Meadowlark.  Top soil and landscape restoration on Meadowlark is scheduled to be completed by mid-August.  DPW crews have begun ditching and stormwater work on Tennyson, north of Manor.  Work on Tennyson north of Manor is scheduled to be completed by the end of next week.  Work on Tennyson, south of Manor, will begin the week of July 29.  Work in this area is scheduled to take approximately 8-10 work days.  Landscape restoration on Tennyson will commence shortly thereafter.  The road repaving work for both roads is scheduled to begin September 9.  All timelines are contingent on weather.  


Jun 14

Ditching Begins

Posted on June 14, 2019 at 4:02 PM by Andy Pederson

Construction Staking